Sottostima dei costi dei progetti di opere pubbliche: errore casuale o intenzionale? (Underestimating Costs in Public Works Projects: Error or Lie?)
Archivio di studi urbani e regionali, no. 82, Milano: Franco Angeli, pp. 1-28.
28 Pages Posted: 20 Jun 2013
Date Written: 2005
Abstract
This article presents results from the first statistically significant study of cost escalation in transportation infrastructure projects. Based on a sample of 258 transportation infrastructure projects worth US$90 billion and representing different project types, geographical regions, and historical periods, it is found with overwhelming statistical significance that the cost estimates used to decide whether such projects should be built are highly and systematically misleading. Underestimation cannot be explained by error and is best explained by strategic misrepresentation, that is, lying. The policy implications are clear: legislators, administrators, investors, media representatives, and members of the public who value honest numbers should not trust cost estimates and cost-benefit analyses produced by project promoters and their analysts.
The English version of this article can be found at: http://www.ssrn.com/abstract=2278415
Die deutsche Version dieses Artikels finden Sie unter: http://www.ssrn.com/abstract=2278383
Den Svenska versionen av denna artikel finns på: http://papers.ssrn.com/abstract=2278382
Note: Downloadable document is in Italian.